Construction Projects


Construction Detours & Updates


  • CSAH 5 (Eagle Lake Road) Multimodal Improvements. See attached newsletter for details.
    last project update: Apr 20, 2016
    Project Summary:  Any questions about this project, please contact Jared Voge, Big Lake Assistant City Engineer 612-756-0326 or Cody Holmes, Project Engineer 612-756-3440.
    PDF PDF reader requiredProject Documents

  • CSAH 11 Recondition from CSAH 24 to CSAH 4
    last project update: Jul 15, 2016
    Project Summary:  The project is scheduled to begin Monday June 6th, with an anticipated end of July completion date. CSAH 11 will be closed and detoured for the duration of the project. For detour information, please refer to the Interactive Road Construction Viewer link above.

    The contractor will complete the second lift of paving, Friday July 15th. The week of July 18-22nd, the contractor will place the final lift of pavement, place the gravel shoulder, and install the swing away mailboxes. Completion is scheduled to be done on or before July 29th.

    PDF PDF reader requiredProject Documents

  • CR 53 Bridge Replacement over the Elk River
    last project update: Jul 15, 2016
    Project Summary:  The project is scheduled to begin Monday June 6th, with an anticipated end of August completion date. The bridge will be closed and detoured for the duration of the project. For detour information, please refer to the Interactive Road Construction Viewer link above.

    The contractor completed placing the beams will pour the concrete deck Friday, July 15th. The week of July 18th-22nd, the contractor will work on the bridge approaches and the concrete railing on the bridge. Week of June 20th

    The contractor finished constructing the east and west abutments. They will be working on the river embankment and placing rip rap the week of June 27th.

    PDF PDF reader requiredProject Documents

  • CSAH 4, Fremont Drive, & Hwy 169 Traffic Signal
    last project update: Jul 15, 2016
    Project Summary:  Friday July 15th, the contractor will close and detour CSAH 4 from Hwy 169 to CSAH 19. The detour will utilize CSAH 19 (104th Street), CSAH 19 (245th Avenue), and Hwy 169. The contractor will remove the pavement on CSAH 4 from Hwy 149 to 1600' east.

    The week of July 18-22nd, the contactor will start reconstructing CSAH 4 from Hwy 169 to 1600' east and start excavating the poor soils under the new alignment of Fremont Drive. See attached newsletter for details.


    PDF PDF reader requiredProject Documents
Public Works Contact:

Sherburne County Govt Center
ATTN: Public Works
13880 Business Center Dr NW
Elk River, MN 55330-1692

Office Location & Hours

Phone: 763-765-3300
800-594-5208
Fax: 763-765-3301

publicworks@co.sherburne.mn.us
Contact Sherburne County with your questions, comments and feedback