Construction Projects


Construction Detours & Updates


  • CSAH 5 from Hwy 10 to Lions Park - Road and Trail Construction
    last project update: Mar 20, 2017
    PDF PDF reader requiredProject Documents

  • CSAH 3 from Hwy 10 to CSAH 20 - Pavement Resurfacing

    CSAH 3 from CSAH 23 to CSAH 11 - Pavement Resurfacing

    CSAH 3 from CSAH 11 to CSAH 5 - Pavement Resurfacing

    last project update: Jun 20, 2017

    Project Summary:  Knife River was awarded the contract for this work. Construction is tentatively scheduled to begin May 8 and be completed by June 16. work will be performed under traffic conditions. No detour will be installed.

    Contractor will start constructing turn lanes the week of May 15. Paving is scheduled to begin week of May 22 on the portion of CSAH 3 from Hwy 10 to CSAH 20.

    CSAH 3 from Hwy 10 to CSAH 20 - Pavement Resurfacing - Work is completed.

    CSAH 3 from CSAH 23 to CSAH 11 - Pavement Resurfacing - Contractor will resume constructing right turn and bypass lanes the week of June 12. Paving is scheduled for first week of July.

    CSAH 3 from CSAH 11 to CSAH 5 - Pavement Resurfacing - Contractor will resume constructing right turn and bypass lanes the week of June 12. Paving is scheduled for the first week of July..

    CSAH 24 from CSAH 23 to the Elk Rive Bridge - Pavement Resurfacing & Reconstruction - Project is scheduled to begin June 26.


  • CSAH 24 from CSAH 23 to the Elk River Bridge - Pavement Resurfacing & Reconstruction
    last project update: Apr 24, 2017
    Project Summary:  Knife River was awarded the contract for this work. Construction is scheduled to begin June 19 and be completed by July 28. CSAH 24 will be closed and detoured. Local traffic will be allowed through the construction zone.

  • CSAH 6 from Hwy 10 to CSAH 16 - Pavement Resurfacing

    CSAH 8 from CSAH 16 to Hwy 24 - Pavement Resurfacing

    CR 72 from CR 35 to CR 32 - Pavement Resurfacing

    CR 75 from CSAH 5 to CSAH 4 - Pavement Resurfacinglast project update: Jun 20, 2017

    Project Summary:  Knife River was awarded the contract for this work. Construction is tentatively scheduled to begin July 10 and be completed by September 15.

    CSAH 6 and CSAH 8 will be performed under traffic conditions. No detour will be installed for these two roads.

    CR 72 and CR 75 will be closed and detoured. Local traffic will be allowed through the construction zone.

    CSAH 6 from Hwy 10 to CSAH 16 - Pavement Resurfacing - Tentatively scheduled to begin the week of July 10.

    CSAH 8 from CSAH 16 to Hwy 24 - Pavement Resurfacing - Tentatively scheduled to begin the week of July 3.

    CR 72 from CR 35 to CR 32 - Pavement Resurfacing - Week of June 18 - the contractor is scheduled to start paving on June 21 and be completed by June 23. Road is closed and detoured.p>

    CR 75 from CSAH 5 to CSAH 4 - Pavement Resurfacing - The contractor is scheduled to start milling the week of June 26.


Public Works Contact:

Sherburne County Govt Center
ATTN: Public Works
13880 Business Center Dr NW
Elk River, MN 55330-1692

Office Location & Hours

Phone: 763-765-3300
800-594-5208
Fax: 763-765-3301

publicworks@co.sherburne.mn.us
Contact Sherburne County with your questions, comments and feedback